Thursday, December 2, 2010

CBC Update

Cheboygan Brewing Company :)

Here is a quick recap of upcoming construction for the next month.

As you can see from the picture, the masonry is basically complete and the bar joists and roof deck are complete. The roof nailer got started on Wednesday and curbs were put down on the roof for HVAC units. Parking lot is graded and set with packed gravel awaiting blacktop in Spring.

Here is what should be happening over the next few weeks until end of year:

- Install roof membrane
- Install underground and pour slab in front
- Frame front and sheath
- Install roof in front
- Install windows and doors
- Install undrground in brewery and pour slab
- Insulate tap room
- Start exterior siding in front
- Pour stamped concrete and aprons

As you can see, we are on the move. The weather thus far has been good with the exception of a couple of days and we remain on schedule.

No comments: